Ashby Clinic & Surestart Centre, Scunthorpe, Lincolnshire

Innovative community collaboration and co-ownership structure

Project: 2 GP Practices / Pharmacy / community based health services / Sure Start / crèche

Size: 2125 sq m

Commenced on-site: January 2005

Completed: April 2006

GPI Project Director: David Sadler, Director North East

Project Architect Design: James Totty Partnership Ltd

Main Build Contractor: Wildgoose Construction Ltd

Employer’s Agent and Planning Supervisor: Summers Inman LLP

A Sure Start facility and crèche run by the local authority are included in the building.

The community facility was designed to incorporate a large number of multi-health, local authority and community users, accessed from one main shared entrance point.

Services within the facility include two GP Practices, dentist and other PCT community based health services.

GPI project managed the construction of the facility including the North Lincolnshire Council element of the scheme and despite its complexities, the new Primary and Community Care facility was completed ahead of time and within budget.

The community also benefits from a retail pharmacy and Café.

“The building is everything you promised it would be and was completed ahead of schedule. In particular I would like to thank you for the minimal disruption caused to the practice and neighbourhood during the building work. I would certainly recommend GPI to any of my colleagues wishing to develop new premises.”

Dr Graham Hayes
Ashby Clinic & Surestart Centre

Ashby Clinic & Surestart Centre, Scunthorpe

Click on plan to enlarge

In Ashby, Scunthorpe, North Lincolnshire, two single handed practices were operating from premises with a chronic lack of space, serious access problems and a number of health and safety issues.

The original aspiration was to bring these two practices together into a modern health centre along with additional facilities to provide a wide range of other community health services in one location. GPI were appointed as preferred developer, having previously completed a new Medical Centre in Scunthorpe.

Following consultation between GPI, the North Lincolnshire PCT and North Lincolnshire Council, the opportunity to integrate and co-locate complementary Council-led services within a larger community facility was identified and explored.

A steering group was formed to work up the vision and planning of the facility. After extensive stakeholder and wider public consultation, an integrated community facility was designed, one that incorporated a large number of multi-health, local authority and community users, accessed from one main shared entrance point rather than multiple service access points.

Services within the facility include two GP Practices, dentist and other PCT community based health services, a Sure Start facility and crèche run by the local authority, a retail pharmacy and Café for the local community.

As North Lincolnshire Council wished to fund their part of the facility through capital rather than revenue, an innovative and fundable shared co-ownership structure also had to be designed by GPI, one made all the more complex through the large amounts of shared public access areas incorporated within the design.

The result is a be-spoke co-ownership structure, in which part of the facility is owned by GPI’s institutional investors and part by North Lincolnshire Council.

GPI project managed the construction of the facility including the North Lincolnshire Council element of the scheme and despite its complexities, the new Primary and Community Care facility was completed ahead of time and within budget.

The strong long term partnership relationship between GPI and the many stakeholders continues through our ongoing management of the facility and of course the innovative co-ownership structure.